Watch

Energy company 'jumps the gun' in appointing transmission line builders

Louise Thrower
Updated December 7 2023 - 5:34pm, first published 1:20pm
CPB Contractors general manager NSW Infrastructure Rob Monaci; GenusPlus Group managing director David Riches; ACCIONA chief operations officer, Andre Noonan; UGL managing director Doug Moss; and Transgrid CEO Brett Redman discuss the HumeLink route. Picture supplied.
CPB Contractors general manager NSW Infrastructure Rob Monaci; GenusPlus Group managing director David Riches; ACCIONA chief operations officer, Andre Noonan; UGL managing director Doug Moss; and Transgrid CEO Brett Redman discuss the HumeLink route. Picture supplied.

TransGrid's decision to award two construction contracts for a major transmission line project has sparked an angry reaction from a lobby group.

Subscribe now for unlimited access.

$0/

(min cost $0)

or signup to continue reading

See subscription options
Louise Thrower

Louise Thrower

Senior journalist

If you have a story to tell, drop me a line at louise.thrower@austcommunitymedia.com.au or call 0418 229 678.

Get the latest Crookwell news in your inbox

Sign up for our newsletter to stay up to date.

We care about the protection of your data. Read our Privacy Policy.